Lucite Alpha 1 Project (8) More..

Project name             : Lucite Alpha 1 Project
Period                     : 1st July 2007 - 31st July 2007
Contract Extension     : 1st August 2007 - 17th August 2007

Cargo Transported:

- Column E1410 - 1 Unit - L23.55 x W2.00 x H2.00m - 27 Tons
- Column E2402 - 1 Unit - L27.70 x W2.20 x H2.20m - 57 Tons each
- Column E3201 - 1 Unit - L30.33 x W2.55 x H2.55m - 59 Tons each
- Column E3401 - 1 Unit - L47.90 x W2.80 x H2.80m - 106 Tons each
- Column E3601 - 1 Unit - L30.90 x W2.20 x H2.20m - 46 Tons each
- Column E3801 - 1 Unit - L26.75 x W2.05 x H2.05m - 46 Tons each
- Column E4201 - 1 Unit - L42.00 x W4.90 x H4.90m - 200 Tons each
- Column D2201A - 1 Unit - L18.00 x W6.10 x H6.10m - 100 Tons each
- Column E2201B - 1 Unit - L18.00 x W6.10 x H6.10m - 100 Tons each

Barge & Tugs Used:

- 1 Unit of L200' x W60' x H12'Barge - 1080HP Tug
- 1 Unit of L200' x W60' x H12'Barge - 1200HP Tug
- 1 Unit of L280' x W80' x H16'Barge - 1700HP Tug

Equipment Used:

- 12 Axlelines Hydraulic Trailer
- 6 Axlelines Self-Propelled Hydraulic Trailer
- 1 unit of 50 Tons Crane
- 800 Tons CC2000 RL Ringer Crane
- 250 Tons Hitachi Sumitomo Crawler Crane
 

Shell Mono Ethylene Glyol Project(MEG Jurong Island) (13) More..

Project name     : Shell Mono Ethylene Glyol Project
                            (MEG Jurong Island)
Location           : PCS II Complex, Jurong Island, Singapore
Period              : March 2008 to November 2008

Cargoes :     

- Dim: L51.80 x W6.54 x H7.66m (389.88 Tons)
- Dim: L62.23 x W8 x H8.5 (196.2 Tons)
- Dim: L24.7 x W10.8 x H9.85 (1,260.0 Tons)
- Dim: L48.6 x W7.5 x H11 (505.1 Tons)
- Dim: L21.32 x W5.3 x H5.92 (301.0 Tons)
- Dim: L13.7 x W5.0 x H6.9 (155 Tons)
- Dim: L17.7 x W5.5 x H6.7 (253.1 Tons)
 

Shell Mono Ethylene Glyol Project(MEG PROJECT) (1)

Project name : Shell Mono Ethylene Glyol Project (MEG PROJECT)
Location         : Malacca, Malaysia to MEG Jetty at Jurong Island, Singapore
Period         : March 2008 to September 2008


 

Singapre Parallel Train Project (4)

Project name         : Singapre Parallel Train Project
Location                : PSA Port to Exxon Mobil Banyan Jetty, Jurong   Island
Year                     : March 2009

Cargo :
                 
: 2 units Reactor ĘC 454.42 Tons each
Dim: L 43.25 x W 8.93 x H 9.07m
2 units Purge Bin ĘC 199.50 Tons each
Dim: L 46.89 x W 7.10 x H 7.22m

Supply Of Equipment

- Tug    :  Yew Choon 2 (2400 Bhp)
              Yew Choon 7 (2400 Bhp)
- Barge :  Yew Choon Marine 7 (L280' x W80' x H16')
              Yew Choon Marine 11(L280' x W80' x H16')
 - Supply of 2 units assist tug
 - Supply of lashing equipments
 - Supply of roro equipment